Rubber Hammer for tapping blocks without damaging the surface
Plate vibrator for final compaction with two to three paves of the plate
LAYING INSTRUCTIONS
Organize all material like blocks, sand, vibrators and cutter.
Plan your schedule to avoid delivery of material before they are needed as they congest the site.
Keep the sand with moisture content; do not use sand which is 100% dry.
Do not spread sand for larger areas, as it will dry out and reduce the performance.
Preferably, use sand of 50mm screeded properly.
Pavers should be laid with hand tight to pattern on screeded layer of 50mm-sand bed.
Spectra Premium Pavers are designed with ‘NIBS’ which provide definite gap between blocks. Dry sand is spread and swept over the area and further vibrated to fill joins.
Complete laying operations like cutting, vibrating and sanding (Joint filling) are to be done on the same day.
Joints should be filled with clean dry sand, so that it flows better and fills joints effectively.
Edge curbing: There should be adequate restraint around the perimeter of all paved area to support traffic loads and to prevent the escape of laying course material from beneath the paved surface.
It is recommended to provide a slope of 3” on the wider side and 2” on the linear side for every 10’ of the laying area.
Disclaimer
The individual dimensions in sq ft, shown, are rounded off to the nearest decimal point.
Colors shown are indicative only. It is advisable to see the actual product.
Color and thickness variations are inherent properties of this industry.
It is advisable to follow the laying instructions before fixing, as no responsibility is accepted by the company once laid.
These Products are subject to standard tolerance as specified in IS: 15658:2006 & IS:1237:2012